Austin, Texas
Electric Vehicle General Assembly Plant
To meet the production requirements of this pioneering EV automaker, Prospect had 10,000 tons of fabricated steel on the ground within 10 weeks of NTP and was substantially complete with erection in 30 weeks. The completed project comes in at 1,600,00 square feet and 40,000 total tons of steel.